1The Scrum Team noticed during the Sprint Review that a few of the Product Backlog Items considered "Done" in the previous sprints did not meet the expectations of the stakeholders. The team realized that their current Definition of Done may be incomplete.
Which Scrum event should they use to discuss and potentially update the Definition of Done to better align with stakeholder expectations?
Which Scrum event should they use to discuss and potentially update the Definition of Done to better align with stakeholder expectations?